Thursday, May 22, 2008
Tuesday, May 20
Randall and 1 other guy arrived late morning and worked until about 3:30. Put in next layer of subflooring on ground floor to match up with current structure.
Brought 2 flat bed trailers with them. Emptied garage of tools. Did not remove garbage from yard or leave bin for waste.
Brought 2 flat bed trailers with them. Emptied garage of tools. Did not remove garbage from yard or leave bin for waste.
Friday, May 16
Met with Jeremy and Randall re: project.
Anticipated completion is late July.
Hold up: Waiting for I Beam for roof. This week they will put in remainder of flooring and start building 2nd floor but waiting for I beam to really complete work.
Committed to status reports on what was to be accomplished the following week on Fridays.
Anticipated completion is late July.
Hold up: Waiting for I Beam for roof. This week they will put in remainder of flooring and start building 2nd floor but waiting for I beam to really complete work.
Committed to status reports on what was to be accomplished the following week on Fridays.
Thursday, May 1, 2008
Thursday, May 1, 2008
Called Jeremy and left a message re: my input on where to put crawlspace and to get an idea of project plan for next week while we are out of town.
Tuesday, April 29, 2008
Inspection happened. Inspector wants a crawlspace cut into the flooring.
WOrker came and got plans to figure out where crawlspace can be located.
WOrker came and got plans to figure out where crawlspace can be located.