Schedule derived on March 17, 2008

Meeting with Jeremy on March 17 outlined the following schedule:
  • Inspect foundation: March 18
  • Move Dirt: March 19 - 21
  • Framing subflooring: (14 days) 3/31 - 4/14
  • Electrical HVAC: (14 days) 4/15 - 4/29
  • Plumbing
  • Sheetrock addition: (2 days) 5/1 - 5/2
  • Tape, mud, sand: (3 days) 5/5 - 5/8
  • Texture (1 day): 5/8 - 5/9
  • Paint (1 day): 5/9
  • Flooring/Carpeting: (2 days)
  • Finish work for kitchen and bath (14 days)
  • Siding (5 days)
  • exterior finish work-Pain exterior (3 days)