- Inspect foundation: March 18
- Move Dirt: March 19 - 21
- Framing subflooring: (14 days) 3/31 - 4/14
- Electrical HVAC: (14 days) 4/15 - 4/29
- Plumbing
- Sheetrock addition: (2 days) 5/1 - 5/2
- Tape, mud, sand: (3 days) 5/5 - 5/8
- Texture (1 day): 5/8 - 5/9
- Paint (1 day): 5/9
- Flooring/Carpeting: (2 days)
- Finish work for kitchen and bath (14 days)
- Siding (5 days)
- exterior finish work-Pain exterior (3 days)
Tuesday, April 22, 2008
Schedule derived on March 17, 2008
Meeting with Jeremy on March 17 outlined the following schedule: